MyPlace - Cedars Youth and Community Centre
Timeline
- Meeting with planning authority: 4 August 2009
- MyPlace bid submission: 26 August 2009
- Planning proposals for review: September 2009
- Planning application: 23 October 2009
- An application for planning permission was submitted and approved. You can view full details by entering the application reference number P/2441/09 or postcode HA3 6QH in the appropriate box on the planning application search. Planning application approved at Planning Committee: 3 February 2010
- Formal proposals were submitted by Harrow Council/ Watford FC's Community Sports and Education Trust to the Department for Children, Schools and Families (DCSF) with a final decision likely in spring 2010.
The Department for Education was formed on 12 May 2010 and is responsible for education and children's services.
- Invite tenders from contractors - 26 July 2010
- Mid tender interviews - 1 September 2010
- Tender returns - 20 September 2010
- Award contract - 11 October 2010
- Date of site possession (for demolition of old building) - 25 October 2010
- Date for completion of project - approximately October 2011 (44 calendar weeks from date of site possession)